Pritchett, Colorado

Pritchett School District

$4.1M EPC at Pritchett School District, modernizing the historic 1938 K–12 facility with energy-efficient HVAC, LED lighting, envelope upgrades, and controls to reduce energy use and generate nearly $6,000 in annual savings.

industry

K-12

location

Pritchett, Colorado

Solutions

Building Performance Compliance, Energy & Operational Efficiency, Energy Audits, Financial Structuring, Incentives, Performance Assurance, Performance Contracting

Annual Savings

$5,791

Annual Energy Savings

749,412 kBtu

Overview

Facing outdated equipment, poor envelope performance, and escalating utility costs, Pritchett School District partnered with our team to complete a BEST grant–funded Energy Performance Contract. The project addressed critical infrastructure needs with new HVAC systems, windows and doors, lighting retrofits, and a building automation system, improving comfort, reliability, and long-term operational sustainability.

Solutions

We replaced outdated lighting, HVAC, and envelope systems with modern, energy-efficient technologies. Upgrades included LED lighting retrofits, condensing boilers, RTUs, unit ventilators, cabinet heaters, a BAS, and full window and door replacements. We also supported grant procurement and provided training, commissioning, and performance verification.

Results

The verified savings totaled $5,791, exceeding the guarantee. Lighting improvements delivered higher-quality illumination and reduced energy use. HVAC upgrades enhanced comfort, reduced gas consumption, and maintained condensing boiler efficiency. Envelope improvements improved building tightness and indoor comfort. Overall, the EPC delivered long-term financial, operational, and occupant comfort benefits.

Project Highlights

  • $4.1M EPC funded primarily through BEST grant
  • Verified annual savings exceed guarantee by $455
  • 31,452 kWh + 6,421 therms energy savings in Year 3
  • Full LED retrofit, including updated exterior wall packs
  • High-efficiency condensing boilers and new HVAC systems
  • New insulated, thermally broken windows and exterior doors
  • BAS upgrades enabling remote monitoring and improved scheduling

Energy Conservation
Measures

  • LED lighting retrofits & occupancy sensor evaluation
  • HVAC system & controls replacement (condensing boilers, RTUs, UVs, CUHs)
  • Complete exterior window replacement with insulated glazing
  • Exterior door replacement and weather sealing
  • Building automation system upgrades

Related Projects

Row midpoint Shape Decorative svg added to bottom

Let’s Build Together

CEG Solutions helps public and private clients modernize infrastructure, achieve deep savings, and enhance energy and operational efficiency — without disrupting mission-critical operations. Let’s talk about what we can achieve together.