NASA Jet Propulsion Laboratory - Phase I-III

CEG completed three phases of energy upgrades at NASA Jet Propulsion Laboratory that have significantly reduced energy and water consumption, increased on-site renewable energy generation, and enhanced site resilience.

Verified Annual Savings: $4.6MM & 61,697MMBTU

Project Highlights

  • Upgrades in 128 Buildings including Laboratories, Data Centers, and Manufacturing Facilities

  • Achieved a deep energy retrofit in B183 (48% energy reduction) and in B238 (47% energy reduction)

  • Secured $700k in utility incentives

  • Achieved measured PUEs of less than 1.25 and 1.35 at two different data center locations

  • Included redundant cooling and a microgrid for mission-critical operations

Energy Conservation Measures

  • DDC upgrades and VAV conversions

  • Daylighting and occupancy controls

  • Spectrally enhanced lighting

  • Water infrastructure upgrades

  • Xeriscaping, irrigation infrastructure, and controls upgrades

  • RO water treatment plant upgrades

  • Rooftop solar PV system

  • Building envelope and window film improvements

  • Chiller/boiler replacement and right-sizing

  • Data center consolidation

  • New server racks, UPS, PDUs, backup generator, and ancillary infrastructure

  • In-rack cooling and alternate high-efficiency cooling equipment

  • Secure microgrid for resiliency

Project Overview

The NASA Jet Propulsion Laboratory (JPL) campus includes more than 150 facilities, some constructed as early as 1945. Many of the facilities host 24/7, mission-critical operations that could not be disrupted at any time during the project. Over 5,000 employees and contractors occupy the facility daily.

This comprehensive ESPC project involved a wide array of ECMs to drive deeper savings and improve overall building performance for 128 occupied, operationally dependent mission-critical facilities. The project also included extensive data center renovations and a new data center to improve data center operational efficiency and resilience.

NASA Realized Significant Non-Energy Benefits

  1. Renewable Energy: CEG installed an on-site 285kW solar photovoltaic system that lessened the Laboratory’s reliance on the power grid.

  2. Resilience: CEG’s energy efficiency upgrades reduced base loads, which decreased demand on JPL’s backup power systems, thus enhancing operational continuity in the event of a grid outage. The project also increased central plant redundancy and installed a microgrid with both generation and battery storage to support critical loads for 3+ days without grid power.

  3. Water Savings: CEG took a comprehensive approach to lab water use and addressed almost all water consuming systems. CEG modified the domestic water system, process water plants, landscaping, irrigation, and cooling towers to reduce water consumption. This resulted

Awards

The project has been recognized by the DOE and AEE for excellence and innovation.

Previous
Previous

NASA Jet Propulsion Laboratory, Phase I-II

Next
Next

NASA Jet Propulsion Laboratory, Data Center